Question 1

Elements calculated in the master scheduling process include:

  • A. service-parts forecast.
  • B. available-to-promise.
  • C. time fences.
  • D. allocations.
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 2

Available-to-promise data facilitates the process of:

  • A. inventory planning.
  • B. capacity planning.
  • C. forecasting.
  • D. order entry.
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 3

A bill of resources typically contains information about a product's:

  • A. inventory balances.
  • B. key work centers.
  • C. production schedule.
  • D. complete list of components.
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 4

Which of the following actions is best for a company to take when a 2-week plant shutdown for
retooling is planned for the next year?

  • A. Increase planned production.
  • B. Increase material requirements planning safety-stock levels.
  • C. Decrease the planned sales level during the shutdown.
  • D. Alter the strategic plan.
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 5

The most effective way to cope with uncertainty of demand and to improve customer service is to
reduce:

  • A. lead times.
  • B. backlogs.
  • C. safety stock.
  • D. product options.
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 6

Which of the following tools is used to accommodate forecast errors when developing the master
production schedule?

  • A. Safety stock
  • B. Planning time fence
  • C. Firm planned orders
  • D. Available-to-promise
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 7

In an assemble-to-order environment, which of the following factors is most significant in
determining which items should be master scheduled?

  • A. Length of the master schedule horizon
  • B. Number of levels in the bill of material
  • C. Number of product options
  • D. Size of the forecast error
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 8

Rough-cut capacity planning is best used to:

  • A. assess the load on a work center.
  • B. evaluate the master production schedule.
  • C. establish order priorities.
  • D. determine labor requirements.
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 9

The question below is based on the following information:

Which of the following weekly production rates best supports these criteria?

  • A. 70
  • B. 78
  • C. 80
  • D. 90
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 10

Translation of a master production schedule directly into key resources results in a:

  • A. production schedule.
  • B. final assembly schedule.
  • C. rough-cut capacity plan.
  • D. bill of labor.
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments