Topic 4
Which of the following would a project manager organize and implement in order to provide decision oversight to scope
changes?
C
Topic 4
A project manager has an initial problem with a remote team members performance. Which of the following is the BEST form
of communication to address this issue?
C
Topic 4
A manager and the head of engineering discuss a change to a major work package. After the meeting, the project manager
contacts a third person and tells them to complete the paperwork to make the change. Who did the project manager contact?
D
Topic 4
During final inspection, a project team member finds a deficiency in the product. In which of the following did this action
occur?
B
Topic 4
Which of the following shows the number of communication channels for a team with twelve stakeholders?
B
Topic 4
Which of the following is the correct progression of the project life cycle?
B
Topic 4
Which of the following is the FINAL step in the pre-project setup phase?
A
Topic 4
An important team member will not be available to complete a project. The project manager selects a new team member and
trains the new team member on the project tasks. The project manager is using which of the following risk response
techniques to resolve the issue?
B
Topic 4
An ongoing project requires several parts manufactured at an outside vendor. If the vendor has sufficient quantity and can
still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days.
Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the
PERT method, which of the following is the correct time estimate for a parts delivery?
B
Topic 4
Which of the following shows a project that is presently over its financial budget?
D
Topic 4
Which of the following is a representation of the difference between the planned costs of work completed compared to the
actual cost at a point in time?
C
Topic 4
Which of the following BEST describes the chart of accounts?
B
Topic 4
Which of the following is the BEST report to provide to senior management?
B
Topic 4
A project manager has received a change request. Which of the following is the NEXT step?
D
Topic 4
A variance between the planned scheduled work and the actual work completed would initially be highlighted in which of the
following performance statistics?
B