Page 1 out of 20. Viewing questions 1-15 out of 296
Question 1
Which is a task of product-based planning?
A.
Identify activities and dependencies
B.
Write the Project Product Description
C.
Prepare the Work Packages
D.
Produce Product Status Accounts
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
Which role is responsible for creating Checkpoint Reports?
A.
Senior Supplier
B.
Team Manager
C.
Change Authority
D.
Project Support
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
How many management stages should a PRINCE2 project consist of?
A.
Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B.
Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C.
Initiation stage and at least one other management stage to cover the remainder of the project
D.
Start up stage, initiation stage and a closing stage
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 4
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
A.
project cost tolerance
B.
stage cost tolerance
C.
Work Package cost tolerance
D.
product cost tolerance
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A.
Configuration Item Record
B.
Quality Register
C.
Highlight Report
D.
Checkpoint Report
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 6
Which is a true statement about PRINCE2 event-driven controls
A.
Event-driven controls take place at predefined periodicintervals
B.
Event-driven controls are produced at the frequency defined in a Work Package
C.
Event-driven controls are used for decision making
D.
Checkpoint Reports are event-driven controls
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans
A.
define a coding system to provide a unique identifier for the products within
B.
summarize the results of the quality activities performed on
C.
provide a framework to design, develop and maintain
D.
define the project benefits to be achieved by each of
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities
A.
change budget
B.
project budget
C.
project's cost tolerance
D.
project's risk tolerance
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
A.
controls
B.
products
C.
project management team
D.
stages
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
Which is NOT considered when defining risk tolerance?
A.
A Project Board's attitude towards risk taking
B.
The allocated risk budget
C.
An organization's risk appetite
D.
The amount of risk a Project Board considers acceptable
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
Which statement about the quality review technique is FALSE?
A.
It enables a check to be made on a product's fitness for purpose
B.
It defines the quality responsibilities of the project team
C.
It supports the management of future changes by providing abaseline for a product
D.
It is used to gain wider acceptance of a product by involving key interested parties
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 12
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A.
A Project Brief
B.
Sufficient information to identify the prospective Executive
C.
The Project Initiation Documentation
D.
Authority to initiate a project
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
Why is it crucial that the Project Product Description clearly defines acceptance methods?
A.
Enables Project Assurance to authorize quality activities
B.
Defines how all project products will be reviewed and approved
C.
Defines how it will be proven that the completed project product meets the customer's expectations
D.
Provides confirmation that all project products have met their quality criteria
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 14
Which of the following statements about customer's quality expectations and acceptance criteria are true? 1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders. 2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
A.
Only 1 is true
B.
Only 2 is true
C.
Both 1 and 2 are true
D.
Neither 1 or 2 are true
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
Which is part of quality control?
A.
Undertake quality reviews
B.
Write Product Descriptions
C.
Provide assurance that the project is being conducted properly